Case Study

Balfour Beatty A63 Project

Background

Balfour Beatty was awarded a $96 million contract as part of a major five-year, $451 million Highways England improvement scheme. A 0.9 mile site in the centre of Hull (Castle Street). The A63 was designed to improve access to the port, congestion, road safety and connections between the city centre and recreation facilities.

By deploying sustainable products across the A63 Improvement Scheme – Balfour Beatty could achieve incredible results, including a major reduction in diesel usage and CO2e emissions.

Challenge

An ancient 300-year-old burial site had to be relocated carefully and respectfully to another site. Balfour Beatty deployed the industry’s first electric mini excavator – saving up to 70% in fuel used. Three electric excavators needed to be recharged each day, including powering the lights and the pump keeping the tent lit up and raised.

Balfour Beatty wanted to reduce the noise and emissions on this protected site. However, there was no mains power on site. A diesel generator running 24/7 was unsuitable for operating in an enclosed space and would eliminate the sustainable and environmental benefits gained by the project so far.

ProPower Single Phase stowed and open overlapping

The Solution

Our revolutionary ProPower Solar Hybrid Generator provided an off-grid temporary power solution. Solar powered meant a reduction in emissions and fuel, reduced noise, and less maintenance was needed. No mains power meant no trenching was required – meaning a fully off-grid power solution.

The generator is fixed to a trailer making it mobile and easily deployable. EV charging can be added, providing one of the many customizable features. The ProPower is favorably used for welfare and site cabin power.

The Result

By replacing diesel generators and upgrading to our sustainable solar hybrid generators – Balfour Beatty achieved incredible results – including a major reduction in noise pollution, diesel usage and CO2e emissions.

The Prolectric ProPower is an off-grid sustainable power solution that has been specially designed to deliver temporary power to various sectors sites.

Carbon Savings

8 tons of CO2e

Fuel Savings

668 gallons of fuel

Zero Fuel Hours

78%

Solar Power Generation

210 kWh

Downloads

Download the Case Study to assist in your business case.

What our clients
have to say

We’re excited to work together
on your next project.

Available for purchase
ProPower single phase stowed