Carbon Savings (kg of CO2e)
Fuel Savings (litres)
Cost Savings
During a recent £135M road project in North Wales Balfour Beatty and Jones Bros joint venture made substantial environmental and commercial savings by deploying Prolectric sustainable products.
The project started in 2014 with construction starting in 2019 and involves the construction of a new bypass to carry the A487 around Caernarfon and the adjacent villages of Llanwnda, Dinas and Bontnewydd. The current route is prone to high traffic congestion at peak times.
The 9.8km route will remove traffic congestion from the existing route and improve commuter journey times.

Noise and air pollution affects the quality of life for residents along the A487 with the high volumes of traffic. As this was already a major issue, reducing the air pollution and noise made by the construction works would be crucial for the residents in the area.
Jones Bros needed an alternative to traditional diesel fuel generators, which would have only added to the problem. During the construction phase the main compound of temporary site offices had grid power. However, as the new bypass is almost 10km in length there was a requirement to provide welfare facilities for workers along the route.
As there is no access to mains power, normally these compounds would be powered by diesel generators that run 24/7. Balfour Beatty and Jones Bros identified that this wasn’t an efficient use of the generators as they are a major contributor to C02 emissions on site.
Download the Case Study to assist in your business case.
The JV welcomed the opportunity to participate in the trial of this new sustainable power solution from Prolectric, confirming it as a viable and more sustainable alternative to traditional generators, and look forward to working with Prolectric again in the future.
Jon Muff
Project Manager, Balfour Beatty
Since the start of the 52-week hire period in July, the ProPower Solar Hybrid Generator engine only ran for around 16% of the time. This substantial reduction in generator usage translated to massive fuel savings and significantly lowered overall emissions on the site. The overall site was powered by solar and battery alone, showcasing the effectiveness of Prolectric’s products in providing sustainable and reliable energy solutions.
Gary Quinton
Project Manager, CLM Construction
Prolectric have been an outstanding supplier in recent months. From point-of-sale to product support, there is nothing I can fault. Their products save our customers a fortune and reduce carbon emissions across sites. A key thing about Prolectric is you’re not left on your own – support is truly unmatched. With special thanks to Nick and Mitch for all their assistance, we now run a small fleet since buying the first unit.
Laura Tudhope
Plant Manager, Askam Civil Engineering
As the off-grid solar lighting and power experts, we offer solutions that are reliable, commercially viable and environmentally responsible.
Call us for an urgent query on 01275 400570,
email us or fill out the short form below.