Background

Magnox are responsible for the safe and secure clean-up of 12 nuclear sites and the operation of one hydro-electric plant. Magnox works with the Nuclear Decommissioning Authority. Their purpose is to manage sites through their lifecycles, overseeing all aspects of operation, defuelling and decommissioning.

Magnox Logo

Challenge

A recent land remediation project at the Winfrith site required a mobile off-grid power source in order to operate an excavator bucket monitoring system and a high resolution gamma spectrometer with a turntable for gamma assay of builder’s bags, required to process 600m3 of soil. The contractor’s equipment required constant power to maintain suitable operating temperatures of the equipment.

The Solution

After the initial concern of suggesting to run a diesel generator 24/7 for the project duration, Magnox hired the ProPower Solar Hybrid Generator. The ProPower was used  as the sole source of power for the project duration of 6 weeks and at no point was the in-built backup diesel engine required. The ProPower successfully met all the power requirements for the entire project, resulting in zero carbon emissions compared to the use of a traditional diesel-generator.

The Result

It is estimated that the use of the ProPower saved approximately 5,000 kg of CO2e and 1,866 litres of diesel over the 6 week project, resulting in savings of over £2,873. Early engagement enabled the Magnox project team to encourage use of a more sustainable solution for a commonly undertaken process. The generator’s  successful utilisation has inspired colleagues to explore the implementation of solar-powered welfare facilities for future site projects.

Downloads

Download the Case Study to assist in your business case.

What our clients
have to say

We’re excited to work together
on your next project.

Available for purchase or hire
ProPower single phase stowed

Prolectric are fully accredited with the following bodies